Menu

HomeAll Real CasesLoan & Debt DisputesProperty & Real EstateContract & BusinessConsumer & Daily
HomeAll Real CasesSchool Ordered to Pay 92,926 Yuan for Unpaid Dormitory Construction Project

School Ordered to Pay 92,926 Yuan for Unpaid Dormitory Construction Project

All Real CasesMay 9, 2026 4 min read

A regional vocational school has been ordered by a court to repay 92,926 yuan to a builder who constructed a student dormitory building under a fixed-price contract signed in 1995, with the debt remaining unpaid for over 15 years.

Overview

The plaintiff, a construction contractor, entered into a contract with a local vocational school in 1995 to build a student dormitory building for a total price of 300,000 yuan. The school’s then-director assured the contractor that payments would be made as work progressed from government funding. However, the school failed to pay according to this arrangement. In 2005, the school issued an acknowledgment of debt for 92,926.10 yuan and confirmed that interest would accrue at bank lending rates. The school subsequently underwent reorganization and merged with another institution, yet the debt was never repaid. The contractor took legal action seeking the principal amount plus accumulated interest.

Background

In March 1995, the contractor signed an agreement with the school to construct a two-story student dormitory. The agreed total contract price was 300,000 yuan, payable as the project advanced. The school’s director at the time reportedly told the contractor not to worry about financing, as government funds would cover payments. Construction proceeded and was completed, but the school did not fulfill its payment obligations. The contractor was forced to cover costs through personal loans and bank borrowings at significant interest rates. Years of broken promises followed as school leadership changed. In August 2005, the school issued a formal debt acknowledgment for 92,926.10 yuan, stamped with the school’s financial seal. A letter from the former director in 2011 confirmed that the debt existed and that bank interest should accrue. The school was subsequently restructured, merging with a neighboring vocational school, but refused to service the debt.

Evidence

The contractor submitted the original construction contract from 1995, the school’s formal debt acknowledgment issued in 2005 with an official seal, and a written statement from the former director confirming the debt and interest arrangement. Bank loan records were presented to demonstrate the financial burden the contractor carried due to delayed payment. The defendant school received formal court notification but chose not to attend the proceedings or submit any counter-arguments.

Court Findings

The court accepted all evidence submitted by the contractor as credible and sufficient. The existence of an enforceable construction contract and the outstanding debt of 92,926.10 yuan were deemed proven beyond dispute. The court determined that the 2005 debt acknowledgment combined with the director’s 2011 confirmation letter constituted a binding agreement on interest terms. The court rejected the defendant’s argument that the merged institution bore no responsibility for the pre-merger debt. The court also declined to hold the local government or the merged school liable for连带责任, as no legal basis for such shared liability was demonstrated.

Legal Analysis

Under Chinese civil law, contracting parties must fulfill their obligations under the agreed terms. Where a debt is acknowledged and a payment date is set, the debtor must pay by that deadline. When payment is overdue, the creditor is entitled to seek interest compensation. The court determined that the defendant school’s debt acknowledgment created a clear and enforceable obligation. The contractual arrangement for bank-rate interest on the outstanding balance was upheld. The lack of evidence linking the other defendants to the original contractual relationship meant those claims were dismissed.

Conclusion

The court ordered the original vocational school to pay 92,926.10 yuan plus interest calculated from August 11, 2005 at the rural credit union lending rate. Court costs of 2,120 yuan were assessed against the defendant. All other claims against the local government and the merged institution were dismissed. The defendant was warned that failure to comply would result in penalty interest at double the standard rate.

Disclaimer: This article is based on publicly available court records and is intended for informational purposes only. It does not constitute legal advice.

This article is rewritten from public court documents for general reading only. It does not constitute legal advice. Consult a qualified attorney for specific legal matters.

All Real CasesLoan & DebtProperty & Real EstateContract & BusinessConsumer & Daily

About UsPrivacy PolicyDisclaimerContactTerms of Service

© 2026 Real Case Legal. All Rights Reserved.