Menu

HomeAll Real CasesLoan & Debt DisputesProperty & Real EstateContract & BusinessConsumer & Daily
HomeAll Real CasesElevator Contract Dispute Leads to Judgment for Unpaid Balance of 14,438 Yuan and 5,154 Yuan in Damages

Elevator Contract Dispute Leads to Judgment for Unpaid Balance of 14,438 Yuan and 5,154 Yuan in Damages

All Real CasesJune 4, 2026 5 min read

Elevator Contract Dispute Leads to Judgment for Unpaid Balance of 14,438 Yuan and 5,154 Yuan in Damages

Case Overview

A Chinese elevator manufacturing company successfully obtained a court judgment against a sports center for an unpaid contract balance of 14,438 yuan plus 5,154 yuan in late payment penalties. The dispute arose from a 2007 contract for the sale and installation of two elevators. The court found the defendant breached the agreement by failing to pay the final installment after the elevators were delivered and certified as operational. The total judgment, including costs, amounted to 19,592 yuan.

Case Background and Facts

In July 2007, the plaintiff elevator company and the defendant sports center entered into two related contracts. The first was a contract for the sale of two elevators at a total price of 288,766 yuan. The second was a contract for the installation of those elevators, with a fee of 26,234 yuan. The combined contract value was 315,000 yuan.

The payment schedule under the sales contract required the defendant to pay 30 percent of the equipment price upon signing. A further 65 percent was due ten days before delivery. The final 5 percent was to be paid within three days after the first anniversary of the acceptance inspection. The installation contract required 50 percent payment three days before installation began, with the remaining 50 percent due within seven days after the installation passed inspection.

The contracts also included a penalty clause. If the defendant failed to make a payment on time, it would owe interest at a rate of 0.03 percent per day on the overdue amount. The total penalty was capped at 5 percent of the total contract price.

Court Proceedings and Evidence

The plaintiff filed its lawsuit in July 2011. The defendant was properly notified of the court proceedings but did not appear in court or submit any defense. The court proceeded with a public hearing in the defendant’s absence.

The plaintiff presented several key pieces of evidence to support its claim. These included the original sales and installation contracts, an official acceptance inspection report, a delivery record for the elevators, and a previous court filing notice showing the plaintiff had attempted to bring this claim earlier in January 2010 but had withdrawn it due to issues with serving the defendant. Because the defendant did not attend the hearing, it waived its right to challenge this evidence. The court accepted all of the plaintiff’s evidence as valid.

The evidence showed that the plaintiff fulfilled its obligations. The elevators were delivered and installed. On September 28, 2007, they passed inspection by the local special equipment supervision authority and were put into use. The defendant made partial payments totaling 300,562 yuan but withheld the final balance of 14,438 yuan. The plaintiff’s attempts to collect this amount through demand and a prior lawsuit were unsuccessful, leading to the current action.

Court Findings and Judgment

The court found that the contracts between the parties were valid and legally binding. Both parties had entered into them voluntarily, and the terms did not violate any laws or regulations. By failing to pay the remaining balance, the defendant was in clear breach of contract.

The court held the defendant liable for both the unpaid principal and the contractual late payment penalty. The plaintiff originally calculated the penalty at 4,370 yuan but revised the figure to 5,154 yuan to account for the ongoing delay. This revised amount was within the contractual cap of 5 percent of the total contract price.

The court ordered the defendant to pay the plaintiff 14,438 yuan for the unpaid contract balance and 5,154 yuan in late payment penalties, for a total of 19,592 yuan. This payment was to be made within ten days of the judgment taking effect. The court also ordered the defendant to pay the litigation costs of 870 yuan, which included the filing fee and the cost of public notice service.

Key Legal Principles

This case illustrates the principle that a valid contract is binding on all parties. The court applied the rule that a party who fails to perform its contractual obligations, specifically the obligation to pay money, is in breach and must compensate the other party. The court also enforced the liquidated damages clause agreed upon by the parties, confirming that such clauses are enforceable as long as they are not in violation of law. The principle that a defendant who fails to appear in court waives its right to contest the plaintiff’s evidence and arguments was also central to the outcome.

Practical Insights

This case demonstrates the importance of clear payment terms and penalty clauses in business contracts. The plaintiff was able to recover its losses because the contracts specified the payment schedule and the consequences of late payment. Businesses should ensure their contracts include similar provisions. The case also shows that courts will enforce a contract even when the defendant does not participate in the proceedings. A plaintiff can obtain a judgment based on its own evidence if the defendant chooses not to appear. Additionally, the case highlights that a party may need to refile a lawsuit if initial service of process is unsuccessful, as the plaintiff did here.

Legal References

Contract Law of the People’s Republic of China, Article 8 (Binding Force of Contracts)
Contract Law of the People’s Republic of China, Article 114 (Liquidated Damages)
Contract Law of the People’s Republic of China, Article 263 (Payment for Work)
Civil Procedure Law of the People’s Republic of China, Article 130 (Default Judgment)

Disclaimer

This article is for informational purposes only and does not constitute legal advice. Consult a qualified attorney for specific legal matters.

This article is rewritten from public court documents for general reading only. It does not constitute legal advice. Consult a qualified attorney for specific legal matters.

All Real CasesLoan & DebtProperty & Real EstateContract & BusinessConsumer & Daily

About UsPrivacy PolicyDisclaimerContactTerms of Service

© 2026 Real Case Legal. All Rights Reserved.