Menu

HomeAll Real CasesLoan & Debt DisputesProperty & Real EstateContract & BusinessConsumer & Daily
HomeAll Real CasesDispute Over Unpaid Elevator Contract Leads to Judgment for 75,800 RMB Plus Interest in Northern China

Dispute Over Unpaid Elevator Contract Leads to Judgment for 75,800 RMB Plus Interest in Northern China

All Real CasesMay 24, 2026 4 min read

Dispute Over Unpaid Elevator Contract Leads to Judgment for 75,800 RMB Plus Interest in Northern China

CASE OVERVIEW
A civil court in Northern China ruled in favor of an elevator company in a contract dispute, ordering the defendant company to pay outstanding amounts of 75,800 RMB for delivered and installed elevators, plus interest losses of 13,909.30 RMB. The judgment was entered on January 24, 2011, after the defendant failed to appear at trial.

CASE BACKGROUND AND FACTS
On May 17, 2008, the plaintiff, an elevator company based in Eastern China, entered into a written contract with a company previously known as Hongtai Pump Industry Co., Ltd. (the predecessor of the defendant). The contract required the plaintiff to supply and install two elevators for a total price of 223,800 RMB, which included both the equipment cost and installation fees. The agreement also specified the payment schedule and other terms. The plaintiff fulfilled its obligations by delivering and installing both elevators as agreed. On December 12, 2008, the two elevators passed inspection and were accepted for use by the relevant authorities. The defendant company later changed its name from Hongtai Pump Industry to its current registered name, Zhejiang XX Co., Ltd. Despite repeated demands, the defendant paid only 148,000 RMB, leaving a balance of 75,800 RMB unpaid.

COURT PROCEEDINGS AND EVIDENCE
The plaintiff filed its lawsuit on December 30, 2010. The court accepted the case on the same day and assigned it to a single judge under the summary procedure. A public hearing was held on January 24, 2011. The plaintiff’s authorized representative attended the hearing. The defendant, although properly served with legal notice, did not appear in court and did not submit any written defense or evidence within the statutory period. The plaintiff submitted three key pieces of evidence: the product order and installation contract, a business registration change record showing the name change from Hongtai Pump Industry to the defendant, and two elevator inspection reports confirming the elevators passed acceptance tests and were put into service. The court found that the evidence met the legal standards of authenticity, legality, and relevance, and accepted it as proof of the plaintiff’s claims.

COURT FINDINGS AND JUDGMENT
The court held that the defendant, as the purchaser, failed to pay the full contract price and installation fees. Under the law, when one party fails to pay the price or remuneration, the other party is entitled to demand payment. The court determined that the defendant was solely responsible for the dispute and must pay the outstanding amount immediately. The court found the plaintiff’s claims had both factual and legal support. Because the defendant was properly summoned but failed to appear without valid reason, the court proceeded with a default judgment. The court ordered the defendant to pay the plaintiff 75,800 RMB in principal and 13,909.30 RMB in interest for delayed payment. The court also ordered additional interest calculated at 0.05% per day from December 23, 2011, until the date of actual payment. The defendant was ordered to bear the court costs of 1,021 RMB. If the defendant fails to pay within the specified period, it must pay double the interest on the overdue amount under the relevant civil procedure law.

KEY LEGAL PRINCIPLES
The court applied Article 107 of the Contract Law of the People’s Republic of China, which states that a party that fails to perform its contractual obligations or performs them in a manner inconsistent with the agreement shall bear liability for breach, including payment of damages. The court also referenced Article 130 of the Civil Procedure Law (2007 version), which permits default judgment when a defendant is properly served but fails to appear. For enforcement purposes, the court cited Article 229 of the same law, which mandates double interest on delayed payment of monetary obligations during the enforcement period.

PRACTICAL INSIGHTS
This case highlights the importance of documenting contractual performance and acceptance. The plaintiff’s submission of the contract, business registration records, and inspection reports was critical to proving its case. The defendant’s failure to respond or appear did not prevent the court from ruling against it. Businesses should note that name changes do not eliminate liability for pre-existing contractual obligations. The successor entity inherits the debts of its predecessor. Additionally, the court’s award of interest from a date prior to the judgment demonstrates that courts may grant compensation for delayed payment even when the contract does not explicitly specify interest terms, relying on statutory provisions.

LEGAL REFERENCES
Contract Law of the People’s Republic of China, Article 107
Civil Procedure Law of the People’s Republic of China (2007 Revision), Article 130 and Article 229

DISCLAIMER
This article is for informational purposes only and does not constitute legal advice. Laws and procedures may vary by jurisdiction. Readers should consult a qualified attorney for advice on specific legal matters.

This article is rewritten from public court documents for general reading only. It does not constitute legal advice. Consult a qualified attorney for specific legal matters.

All Real CasesLoan & DebtProperty & Real EstateContract & BusinessConsumer & Daily

About UsPrivacy PolicyDisclaimerContactTerms of Service

© 2026 Real Case Legal. All Rights Reserved.