Menu

HomeAll Real CasesLoan & Debt DisputesProperty & Real EstateContract & BusinessConsumer & Daily
HomeAll Real CasesDesign Firm Loses Appeal in $29,000 Commission Dispute Over Delayed Deliverables

Design Firm Loses Appeal in $29,000 Commission Dispute Over Delayed Deliverables

All Real CasesJune 19, 2026 4 min read

Design Firm Loses Appeal in $29,000 Commission Dispute Over Delayed Deliverables

Case Overview
A design company in Eastern China lost its appeal in a contract dispute with a toy manufacturer, where the court found the design firm had breached the agreement by failing to deliver work on time. The appellate court upheld the trial court’s decision, rejecting claims for unpaid fees and damages.

Case Background and Facts
In March 2007, a design company (Mr. Lanz) and a toy company (Mr. Da) entered into a written agreement for the creation of a visual identity system and a financing business plan. The total contract value was 200,000 RMB (approximately $29,000). The agreement outlined a three-phase delivery schedule with specific payment milestones. Mr. Da paid an initial deposit of 60,000 RMB upon signing. The design firm was obligated to ensure the brand logo and other elements were original and registrable. The contract stipulated a 75-working-day timeline for the entire project, with Mr. Da’s review and revision time excluded from this period.

Court Proceedings and Evidence
Mr. Lanz filed a lawsuit in the trial court, alleging that Mr. Da had breached the contract by failing to pay the second and third installments. Mr. Lanz sought an order for specific performance, payment of 100,000 RMB in outstanding fees, and 30,000 RMB in liquidated damages. The trial court dismissed all claims, finding that Mr. Lanz had breached the contract first by delivering work late and incompletely. Mr. Lanz appealed this decision. During the appeal, Mr. Lanz submitted three new pieces of evidence, including email correspondence, to support its claims about timely delivery and revisions. Mr. Da objected to these as untimely. The appellate court, however, considered the emails relevant to the case and admitted them as evidence, noting the parties had a history of communicating through email.

Court Findings and Judgment
The appellate court reviewed the facts and found that Mr. Lanz had indeed delivered the first-phase design (the logo) via email on March 22, 2007. However, the logo underwent multiple revisions, and the final version was not agreed upon until June 22, 2007. The court held that the clock for the second-phase deliverables should start from this later date. The evidence showed Mr. Da received a set of 77 VI design drawings on July 28, 2007, which was within the 40-working-day timeframe. Regarding the financing plan, Mr. Lanz failed to prove it was delivered on time. A receipt from Mr. Da dated September 23, 2007, stated that the second payment would be made three days after receipt of the financing plan draft. Mr. Lanz could not prove delivery before this date or that later deliveries (on November 1 and December 12) were accepted. The court concluded that both parties shared responsibility for the delivery dispute but that Mr. Lanz’s failure to prove timely performance meant Mr. Da was not in breach. The court also found that the contract could no longer be fulfilled as intended, so it refused to order specific performance. The appeal was dismissed, and the original judgment was affirmed.

Key Legal Principles
The court applied the principle of sequential performance, where a party who has not performed its own obligations cannot demand performance from the other party. The court also addressed the burden of proof, holding that the party claiming delivery must provide sufficient evidence, such as signed receipts or delivery confirmations. The court recognized that emails could be valid evidence of performance if consistent with the parties’ course of dealing. The court distinguished between a contract dispute and a trademark ownership dispute, declining to address the latter in this case.

Practical Insights
This case illustrates the critical importance of clear documentation in contract performance. Parties should obtain written acknowledgments for all deliverables, especially when deadlines are involved. When a project involves revisions, the parties should agree in writing on how revision time will be tracked and how it affects the original timeline. Relying on oral agreements or informal email exchanges without clear acceptance can lead to disputes. The case also shows that courts will not compel continued performance of a contract when the relationship has broken down and the original purpose cannot be achieved.

Legal References
Civil Procedure Law of the People’s Republic of China (2007 Revision), Article 153, Paragraph 1 (concerning the grounds for appellate review and judgment).

Disclaimer
This article is for informational purposes only and does not constitute legal advice. Consult a qualified attorney for specific legal matters.

This article is rewritten from public court documents for general reading only. It does not constitute legal advice. Consult a qualified attorney for specific legal matters.

All Real CasesLoan & DebtProperty & Real EstateContract & BusinessConsumer & Daily

About UsPrivacy PolicyDisclaimerContactTerms of Service

© 2026 Real Case Legal. All Rights Reserved.