Menu

HomeAll Real CasesLoan & Debt DisputesProperty & Real EstateContract & BusinessConsumer & Daily
HomeAll Real CasesCourt Orders Payment of CNY 16,530 in Construction Subcontract Dispute

Court Orders Payment of CNY 16,530 in Construction Subcontract Dispute

All Real CasesMay 14, 2026 3 min read

A court in Eastern China City has ruled in favor of a subcontractor seeking payment of an outstanding balance for road construction work. The dispute arose after a construction company failed to pay the final agreed amount for water drainage work performed under a subcontract arrangement. The court found that the company was liable for the remaining sum despite having undergone a corporate name change during the period in question.

The plaintiff, Mr. Li, entered into an oral subcontract with the defendant’s predecessor company in March 2007 to carry out water ditch work on a national highway improvement project. The parties agreed on unit prices, completion dates, and payment terms. Mr. Li completed the work on schedule. On July 27, 2007, the defendant’s project department calculated the total amount due as CNY 388,354. The defendant made a partial payment of CNY 371,824 on January 28, 2008. Later, on June 7, 2011, after negotiations between the parties, Mr. Li agreed to accept a final settlement amount of CNY 16,530 for the remaining balance. Despite repeated requests, the defendant refused to pay, citing non-payment by the project owner.

The case proceeded to trial in December 2011 under a simplified procedure. Mr. Li appeared in court and presented evidence, including payment receipts, a project settlement statement, a final payment confirmation document, and records of the defendant’s corporate name change. The defendant, a construction company originally registered under a different name in Eastern China City and later renamed in July 2010, failed to appear at the hearing despite proper legal notice. The court conducted the trial in the defendant’s absence.

The court found that a valid construction subcontract existed between Mr. Li and the defendant’s predecessor. Mr. Li had fulfilled his contractual obligations by completing the work on time. The court noted that the defendant’s change of corporate name in July 2010 did not affect its liability for debts incurred under the prior name. The court also recognized Mr. Li’s decision to waive his claim for interest on the overdue payment as a voluntary exercise of his civil rights, which was permissible.

Under the Contract Law of the People’s Republic of China, the court held that a party that has performed its contractual duties is entitled to receive the agreed consideration. The defendant’s obligation to pay the remaining balance arose from the subcontract relationship, and the name change did not extinguish this debt. The court further stated that the defendant’s failure to raise any defense or attend the hearing did not relieve it of liability. The legal principle that a change in corporate identity does not discharge existing contractual obligations was central to the decision.

The court ordered the defendant to pay Mr. Li the sum of CNY 16,530 within ten days of the judgment taking effect. If the payment is delayed, the defendant must pay double the interest on the overdue amount as prescribed by law. The defendant was also ordered to bear the court costs. This case illustrates that subcontractors can enforce payment agreements even when the contracting company has changed its name. It also shows that courts will respect a party’s decision to waive interest claims as part of a settlement.

Disclaimer: This article is for informational purposes only and does not constitute legal advice.

This article is rewritten from public court documents for general reading only. It does not constitute legal advice. Consult a qualified attorney for specific legal matters.

All Real CasesLoan & DebtProperty & Real EstateContract & BusinessConsumer & Daily

About UsPrivacy PolicyDisclaimerContactTerms of Service

© 2026 Real Case Legal. All Rights Reserved.