Menu

HomeAll Real CasesLoan & Debt DisputesProperty & Real EstateContract & BusinessConsumer & Daily
HomeAll Real CasesConstruction Subcontractor Awarded 305,943 RMB Unpaid Balance in Eastern China Dispute

Construction Subcontractor Awarded 305,943 RMB Unpaid Balance in Eastern China Dispute

All Real CasesJune 13, 2026 4 min read

Construction Subcontractor Awarded 305,943 RMB Unpaid Balance in Eastern China Dispute

Case Overview
A construction subcontractor in Eastern China successfully recovered an unpaid balance of 305,943 RMB plus interest after completing bridge and revetment work on a road project. The court rejected the main contractor’s arguments that the project was not settled and that a disputed payment document was forged, upholding the trial court’s decision in favor of the subcontractors.

Case Background and Facts
In 2006, a construction company (the appellant) was awarded a contract by an economic development zone management committee to build a road, drainage system, bridges, and revetments in an industrial area of Eastern China. The appellant, through its project department manager, entered into a labor subcontract with an individual named Mr. Niu, who lacked formal construction qualifications. Under that agreement, Mr. Niu was responsible for labor and equipment costs while the appellant supplied all materials.

In January 2007, Mr. Niu, acting under the project department’s name, subcontracted the bridge and revetment work to two individuals, Mr. Yu and Mr. Yu, on a labor-only basis for a total price of 780,000 RMB. The subcontractors formed a partnership and mobilized workers and equipment to perform the work.

In January 2008, the appellant’s project department, Mr. Niu, and the two subcontractors signed a supplementary agreement. This agreement transferred the bridge and revetment labor contract directly to the subcontractors and established that the project department would pay them directly at a rate of 24 percent of the total construction cost. The agreement also specified payment percentages for cofferdam expenses related to the bridge and revetment work.

Court Proceedings and Evidence
The subcontractors filed suit in the trial court seeking payment of the outstanding balance. The appellant argued that the project had not been settled and that a wage settlement statement dated March 11, 2008, was a forgery. The trial court ordered a forensic document examination, which confirmed that the seal on the settlement statement matched the appellant’s project department seal.

The settlement statement showed total wages of 877,163 RMB for the bridge and revetment work. The appellant had already paid 501,220 RMB, and an additional 70,000 RMB was deducted for compensation to an injured worker, leaving a balance of 305,943 RMB.

The appellant also claimed that the subcontractors caused project delays. However, a project delay report submitted by the appellant to the project owner, and confirmed by the owner, attributed the delay to land acquisition issues and the need to build a temporary construction bridge.

Court Findings and Judgment
The trial court found that the subcontractors had performed their obligations under the contract and that the project had passed final inspection. The court determined that the wage settlement statement, confirmed by forensic examination as genuine, was a valid basis for calculating the amount owed. The court rejected the appellant’s delay claim, noting that the appellant itself had reported the delays were caused by factors outside the subcontractors’ control.

The trial court ordered the appellant to pay 305,943 RMB in unpaid project funds plus interest calculated from May 12, 2009, at the benchmark interest rate set by the People’s Bank of China. The appellant appealed.

The appellate court affirmed the trial court’s decision. It held that the wage settlement statement, bearing a genuine seal and supported by forensic evidence, was admissible as proof of the settlement amount. The court rejected the argument that the overall project completion date should determine the subcontract’s completion date. The court also found no evidence that the parties had settled all outstanding amounts in a separate personal injury case, as the appellant claimed.

Key Legal Principles
A valid seal on a document, confirmed by forensic examination, creates a presumption of authenticity that can only be overcome by strong contrary evidence. A contractor who accepts the benefits of a subcontractor’s work must pay for that work even if the original subcontract was with an unlicensed intermediary. Project delay reports submitted by a contractor to the project owner can be used as evidence against that contractor in a dispute with its subcontractor.

Practical Insights
Subcontractors should ensure that all payment documents are properly sealed and, where possible, obtain independent verification of signatures and seals. Contractors should be aware that documents they create for other purposes, such as delay reports to project owners, may later be used as evidence in disputes with subcontractors. A settlement in one legal matter does not automatically resolve all outstanding financial issues between the parties unless the settlement agreement clearly states otherwise.

Legal References
Contract Law of the People’s Republic of China, Articles 60, 107, and 109. Supreme People’s Court Interpretation on Issues Concerning the Application of Law in Trial of Cases Involving Construction Project Contract Disputes, Articles 2, 17, and 18. Civil Procedure Law of the People’s Republic of China, Article 153, Paragraph 1, Item 1.

Disclaimer
This article is for informational purposes only and does not constitute legal advice. Consult a qualified attorney for specific legal matters.

This article is rewritten from public court documents for general reading only. It does not constitute legal advice. Consult a qualified attorney for specific legal matters.

All Real CasesLoan & DebtProperty & Real EstateContract & BusinessConsumer & Daily

About UsPrivacy PolicyDisclaimerContactTerms of Service

© 2026 Real Case Legal. All Rights Reserved.