Menu

HomeAll Real CasesLoan & Debt DisputesProperty & Real EstateContract & BusinessConsumer & Daily
HomeAll Real CasesConstruction Dispute Over Unpaid Project Fees Results in Judgment for 1.07 Million Yuan in Eastern China

Construction Dispute Over Unpaid Project Fees Results in Judgment for 1.07 Million Yuan in Eastern China

All Real CasesMay 22, 2026 5 min read

Construction Dispute Over Unpaid Project Fees Results in Judgment for 1.07 Million Yuan in Eastern China

CASE OVERVIEW

A construction company in Eastern China sued a real estate developer for unpaid project fees totaling 4.53 million yuan plus interest. The court ruled the developer must pay the remaining balance of 1.37 million yuan based on a court-ordered audit, but denied the request for late payment interest.

CASE BACKGROUND AND FACTS

Mr. Hu, legal representative of Zhejiang Tiangong Construction Group Co., Ltd. (Tiangong Company), entered into a construction contract with Weicheng Company, a real estate developer in Eastern China. The contract covered the construction of a residential project known as Weicheng-Jinjiang Peninsula Phase I Row Houses, Section II, Buildings 1 through 9. The agreement specified the scope of work, project timeline, quality standards, payment methods, and default responsibilities.

Construction began on January 1, 2005, with a scheduled completion period of 200 days. The project was ultimately completed and passed inspection on January 24, 2006. Tiangong Company submitted a final settlement report to Weicheng Company in November 2006, claiming the total project cost was 12.9 million yuan. Weicheng Company rejected this figure and commissioned its own audit, which produced a preliminary valuation of 9.92 million yuan. Tiangong Company refused to accept this result.

By June 2009, Weicheng Company had paid 9.4 million yuan to Tiangong Company. Dissatisfied with the payment amount, Tiangong Company commissioned its own audit in October 2009, which valued the project at 13.93 million yuan. Tiangong Company then filed a lawsuit seeking payment of the alleged outstanding balance of 4.53 million yuan plus interest of 518,100 yuan.

COURT PROCEEDINGS AND EVIDENCE

The court conducted hearings on February 25, 2010, and January 20, 2011. Both parties presented extensive evidence. Tiangong Company submitted the construction contract, supplementary agreements, design meeting minutes, change orders, construction reports, completion reports, quality inspection records, and payment receipts. Weicheng Company countered with evidence of delayed completion, quality defects requiring repairs by third parties, and correspondence demanding remedial work.

A critical dispute arose over the actual completion date. Tiangong Company presented inspection records suggesting the project passed inspection on November 20, 2005, but the court found evidence of tampering with the dates on these documents. Weicheng Company demonstrated that the actual inspection date was January 24, 2006.

The court appointed Shaoxing Hongyang Project Management Co., Ltd. as an independent auditor to assess the project value. The court-ordered audit determined the total construction cost to be 10,773,432 yuan. Both parties acknowledged the authenticity of this audit, though Tiangong Company argued the valuation was too low.

COURT FINDINGS AND JUDGMENT

The court found the construction contract valid and legally binding. Tiangong Company completed the project and passed inspection, entitling it to payment. However, the court adjusted the claimed amount downward based on the independent audit.

Under the contract terms, Weicheng Company was required to pay 80 percent of the project cost within one week of completion and submission of complete documentation. The remaining 15 percent, minus warranty funds, was due within two months after the audit report, with the warranty fund payable after the five-year warranty period expired. Since the five-year warranty period had elapsed, the court ordered full payment of the remaining balance.

The court calculated that Weicheng Company had paid 9.4 million yuan, which exceeded 80 percent of the audited total of 10.77 million yuan. Therefore, Weicheng Company had not breached the payment schedule, and no late payment interest was warranted.

The court rejected Weicheng Company’s request to deduct utility fees and penalties for construction delays, as these claims were not raised through a formal counterclaim.

The judgment ordered Weicheng Company to pay Tiangong Company 1,373,432 yuan within ten days of the judgment taking effect. All other claims by Tiangong Company were dismissed. Court costs of 47,137 yuan were allocated, with Tiangong Company bearing 29,976 yuan and Weicheng Company bearing 17,161 yuan.

KEY LEGAL PRINCIPLES

This case illustrates several fundamental principles of Chinese construction contract law. The court applied Article 84 of the General Principles of Civil Law, which establishes that debts must be fulfilled. Articles 60 and 279 of the Contract Law require parties to fully perform their contractual obligations and mandate payment upon project completion and inspection.

The case also demonstrates that courts will order independent audits when parties dispute project valuations. The court-ordered audit carries significant evidentiary weight and will typically form the basis for the final judgment.

PRACTICAL INSIGHTS

Construction companies should maintain accurate records of project completion dates and ensure that inspection documents are properly executed without alterations. Any changes to dates on official documents may undermine credibility.

Developers seeking to deduct expenses or assert counterclaims for delays or defects should file formal counterclaims during litigation rather than simply raising objections during trial.

Both parties should be aware that unilateral audits commissioned without mutual agreement may carry limited weight in court proceedings. Court-ordered audits provide a more reliable basis for resolving valuation disputes.

LEGAL REFERENCES

General Principles of Civil Law of the People’s Republic of China, Article 84, Paragraph 1
Contract Law of the People’s Republic of China, Articles 60, Paragraph 1 and 279, Paragraph 1

DISCLAIMER

This article is for informational purposes only and does not constitute legal advice. Laws and regulations vary by jurisdiction, and readers should consult qualified legal professionals for advice specific to their circumstances.

This article is rewritten from public court documents for general reading only. It does not constitute legal advice. Consult a qualified attorney for specific legal matters.

All Real CasesLoan & DebtProperty & Real EstateContract & BusinessConsumer & Daily

About UsPrivacy PolicyDisclaimerContactTerms of Service

© 2026 Real Case Legal. All Rights Reserved.