Menu

HomeAll Real CasesLoan & Debt DisputesProperty & Real EstateContract & BusinessConsumer & Daily
HomeAll Real CasesConstruction Company Ordered to Pay 440,643 Yuan in Rental Fees for Steel Tubes and Fasteners

Construction Company Ordered to Pay 440,643 Yuan in Rental Fees for Steel Tubes and Fasteners

All Real CasesJune 4, 2026 5 min read

Construction Company Ordered to Pay 440,643 Yuan in Rental Fees for Steel Tubes and Fasteners

Case Overview

A construction company in Eastern China was ordered by the appellate court to pay outstanding rental fees of 440,643 yuan plus interest to a trading company for the use of steel tubes and fasteners. The dispute arose from a lease agreement signed in 2004 between the trading company and a project department of the construction company. The court rejected the construction company’s arguments that the claim was time-barred and that the project department lacked authority to enter into the contract. The appellate court affirmed the lower court’s decision, holding that the project department’s actions constituted apparent authority, binding the parent company.

Case Background and Facts

In December 2004, a trading company (the plaintiff, referred to as the Lessor) entered into a lease agreement with a project department of a construction company (the defendant, referred to as the Lessee). The project department was a branch of the construction company and was located in Eastern China. The contract specified the quantity of steel tubes and fasteners, rental prices, and payment terms. The agreement was signed by Mr. Jin, who was identified as the project department’s representative, and designated Mr. Chen as the person responsible for receiving the rented materials.

The Lessor delivered the steel tubes and fasteners as agreed. The rental relationship ended on October 27, 2007. After reconciliation, the total rental fees amounted to 840,643 yuan. The Lessee made partial payments totaling 400,000 yuan, leaving an outstanding balance of 440,643 yuan. The Lessor made multiple demands for payment, including in-person requests to the project department in September 2008, January 2009, and July 2010, as well as formal letters sent by courier in June 2009 and June 2010. When these efforts failed, the Lessor filed a lawsuit seeking the unpaid rent and late payment penalties.

Court Proceedings and Evidence

The Lessee argued that it had never signed any lease agreement with the Lessor and had no business relationship with it, claiming the project department lacked authority to enter into such contracts. The Lessee further contended that the lease ended in August 2005, making the claim time-barred under the statute of limitations. It also disputed the validity of 13 settlement sheets presented by the Lessor, arguing they were submitted after the deadline for evidence and lacked proper confirmation.

The Lessor countered that the last rental date was August 2005 but that the rental relationship continued until October 2007. It argued that Mr. Jin, as the project department’s manager, and Mr. Chen, as the authorized receiver, had apparent authority to confirm the debt. The Lessor also presented evidence of payment demands made to the project department and the construction company.

The trial court found the lease agreement valid and that the project department’s representatives acted within their apparent authority. The court reduced the contractual late payment penalty from 5 per thousand per day to twice the bank loan benchmark interest rate, finding the original rate excessive.

Court Findings and Judgment

The appellate court affirmed the trial court’s decision. It held that the lease agreement between the Lessor and the project department was legally valid. The court found that the Lessee did not challenge the authenticity of the project department’s seal during the trial and had made partial rent payments, which indicated acceptance of the contract. The court determined that Mr. Jin was the project department’s manager and Mr. Chen was the authorized receiver, making their actions official acts of the project department.

Since the project department lacked independent legal status, its legal obligations fell on the parent construction company. The court rejected the statute of limitations defense, noting that the contract did not specify a return date or duration for the leased items. The rental relationship was continuous and indefinite, and the Lessor could not have known its rights were violated at the time of the last rental. Additionally, Mr. Jin confirmed the debt in settlement sheets signed in January 2009 and July 2010, which interrupted the limitation period.

The appellate court ordered the construction company to pay the full outstanding rent of 440,643 yuan plus late payment interest calculated at twice the bank loan benchmark rate from November 27, 2007, until full payment. The court also ordered the construction company to bear all court costs.

Key Legal Principles

The court applied the principle of apparent authority, holding that a third party reasonably relied on the project department manager’s authority to bind the parent company. The court also addressed continuous contracts, ruling that the statute of limitations begins when the party knows or should know its rights are violated, not necessarily at the time of the last transaction in a continuous relationship. The court further held that contractual late payment penalties must be reasonable and can be reduced if excessive.

Practical Insights

This case highlights the importance of clearly defining the scope of authority for project department representatives in construction contracts. Companies should ensure that branch offices and project departments have written authorization limiting their ability to bind the parent company. For lessors, maintaining detailed records of all transactions, payments, and communications is critical for proving continuous business relationships and interrupting limitation periods. The case also demonstrates that courts will enforce contracts signed by apparent agents when the principal has accepted partial performance.

Legal References

Civil Procedure Law of the People’s Republic of China (2007 Revision), Article 153, Paragraph 1.

Disclaimer

This article is for informational purposes only and does not constitute legal advice. Consult a qualified attorney for specific legal matters.

This article is rewritten from public court documents for general reading only. It does not constitute legal advice. Consult a qualified attorney for specific legal matters.

All Real CasesLoan & DebtProperty & Real EstateContract & BusinessConsumer & Daily

About UsPrivacy PolicyDisclaimerContactTerms of Service

© 2026 Real Case Legal. All Rights Reserved.