Menu

HomeAll Real CasesLoan & Debt DisputesProperty & Real EstateContract & BusinessConsumer & Daily
HomeAll Real CasesCourt of Appeal Rules on Breach of Design Contract Involving 200,000 RMB Fee

Court of Appeal Rules on Breach of Design Contract Involving 200,000 RMB Fee

All Real CasesJune 20, 2026 5 min read

Court of Appeal Rules on Breach of Design Contract Involving 200,000 RMB Fee

Case Overview

A design company in Southern China appealed a lower court decision that found it in breach of a contract with a toy company for a visual identity system and business plan. The appellate court reversed part of the ruling, holding that the design company did not owe违约金 (liquidated damages) for delayed delivery of the design work. The court upheld the termination of the contract but dismissed the toy company’s claim for damages.

Case Background and Facts

In March 2007, a design company (referred to as Mr. Lan’s company) and a toy company (referred to as Mr. Lin’s company) entered into a written agreement. The toy company commissioned the design company to create a comprehensive visual identity (VI) system and a financing business plan. The total contract price was 200,000 RMB. The contract specified a three-phase work schedule totaling 75 working days, excluding time for revisions by the toy company. Payment was structured in four installments: 30% (60,000 RMB) upon signing, 30% upon delivery of the second phase draft, 20% upon delivery of the final printed manuals, and 20% within six months of acceptance. A liquidated damages clause provided that any breaching party would pay the other party 30,000 RMB.

The toy company paid the initial 60,000 RMB deposit on the day the contract was signed. The design company completed the first phase, delivering a logo design and basic system. The toy company applied for trademark registration for the logo, named “Marshal Tian Yuan,” in July 2007, which was accepted by the trademark office.

Court Proceedings and Evidence

The design company initially sued the toy company for payment and damages but later withdrew its claim. The toy company then filed a counterclaim seeking contract termination, return of the 60,000 RMB deposit, and 30,000 RMB in liquidated damages.

In the first instance, the lower court found the design company had delayed delivery of the second phase and failed to deliver the store design portion and the financing plan on time. It ordered the design company to pay 30,000 RMB in liquidated damages but rejected the toy company’s request for return of the deposit.

The design company appealed, arguing it had performed its obligations. It submitted new evidence in the appeal, including emails exchanged between the parties. These emails showed that the logo design underwent multiple revisions until June 2007, when the final version was approved. The emails also indicated that the design company delivered 77 VI design drawings in July 2007 and that the toy company acknowledged receipt. The toy company objected to the new evidence but did not provide counter-evidence.

The appellate court accepted the emails as credible, noting that email communication was consistent with the parties’ practice given their geographical distance.

Court Findings and Judgment

The appellate court disagreed with the lower court’s finding of breach by the design company regarding the VI design delivery. It held that the revision period for the logo should not count toward the design company’s deadline. Since the logo was finalized in June 2007, the 40-working-day period for the second phase began after that date. The delivery of 77 design drawings in July 2007 was within the contract timeline.

Regarding the financing plan, the court found the evidence was insufficient to determine whether the design company delivered it on time. The design company claimed it submitted the plan in March 2007 but could not prove actual delivery. The toy company acknowledged receiving it only in December 2007. Neither party provided clear proof of timely delivery or a request for delivery. Therefore, the court ruled that the toy company failed to prove the design company breached the contract for late delivery of the plan.

The appellate court maintained the termination of the contract because the parties’ disputes made continued performance impossible. However, it reversed the award of 30,000 RMB in liquidated damages, finding no clear breach by the design company.

Key Legal Principles

The court applied the principle that the burden of proof rests on the party alleging a breach of contract. The toy company, as the counterclaimant, had to prove the design company failed to perform on time. The court also emphasized that contract deadlines should be calculated excluding time spent on the client’s revisions. Additionally, the court recognized that email evidence can be admissible and credible when consistent with the parties’ business practices and not rebutted by the opposing party.

Practical Insights

This case highlights the importance of maintaining clear records of all communications and deliveries in a service contract. Design companies and clients should document each phase of work, including revisions and approvals, to avoid disputes over deadlines. The ruling also shows that courts will consider the practical realities of a working relationship, such as the use of email for remote collaboration. Parties should be aware that failing to provide evidence of delivery or receipt can result in the court finding neither side has proven its case on that issue.

Legal References

Civil Procedure Law of the People’s Republic of China (2007 Revision), Article 153, Paragraph 1, Item (3)
Supreme People’s Court Regulations on Evidence in Civil Proceedings, Article 2, Paragraph 1

Disclaimer

This article is for informational purposes only and does not constitute legal advice. Consult a qualified attorney for specific legal matters.

This article is rewritten from public court documents for general reading only. It does not constitute legal advice. Consult a qualified attorney for specific legal matters.

All Real CasesLoan & DebtProperty & Real EstateContract & BusinessConsumer & Daily

About UsPrivacy PolicyDisclaimerContactTerms of Service

© 2026 Real Case Legal. All Rights Reserved.