Menu

HomeAll Real CasesLoan & Debt DisputesProperty & Real EstateContract & BusinessConsumer & Daily
HomeAll Real CasesHarbin Construction Dispute: 4.14 Million Yuan Liquidated Damages Claim Rejected by Supreme Court of China

Harbin Construction Dispute: 4.14 Million Yuan Liquidated Damages Claim Rejected by Supreme Court of China

All Real CasesJune 19, 2026 5 min read

Harbin Construction Dispute: 4.14 Million Yuan Liquidated Damages Claim Rejected by Supreme Court of China

Case Overview

The Supreme People’s Court of China, through the High People’s Court of Northern China, rejected a construction company’s claim for 4,142,810.49 yuan in liquidated damages for alleged construction delays. The court found that the employer’s own failure to pay progress payments on time, combined with design changes and site errors, justified the contractor’s extended timeline. The case clarifies how Chinese courts apply the principle of concurrent delay and the requirement for strict compliance with payment obligations in construction contracts.

Case Background and Facts

In June 2002, Zhongshan Construction Company (Mr. Zhongshan) and Xing’an Construction Company (Mr. Xing’an) entered into a construction contract for a teacher’s collective residential building in Northern China. The contract specified a completion date of October 15, 2003, with a penalty of 1 percent of the total contract price for each day of delay. The contract also required Mr. Zhongshan to pay 50 percent of the total project cost upon completion of the main structure’s roof sealing.

During construction, Mr. Zhongshan provided incorrect elevation data, forcing Mr. Xing’an to perform secondary excavation. Additionally, Mr. Zhongshan ordered changes to the balcony design in April 2003. Mr. Xing’an completed the project on October 30, 2003, and submitted a final settlement showing a total project cost of 8,123,157.83 yuan. Mr. Zhongshan paid only 1,720,410 yuan by May 15, 2003, the date the main structure’s roof was sealed, far below the 4,061,578.91 yuan required under the contract.

In January 2007, Mr. Zhongshan sued Mr. Xing’an, claiming 4,142,810.49 yuan in liquidated damages for a 51-day delay. Mr. Xing’an argued that Mr. Zhongshan’s own payment defaults and the design changes justified the extended timeline.

Court Proceedings and Evidence

The trial court in Northern China found that Mr. Zhongshan failed to pay the required 50 percent progress payment by the time the main structure’s roof was sealed on May 15, 2003. The court also noted that Mr. Zhongshan’s elevation error and balcony design changes increased the contractor’s workload, providing a valid basis for an extension. The court rejected Mr. Zhongshan’s claim, holding that Mr. Xing’an did not breach the contract.

Mr. Zhongshan appealed to the High People’s Court of Northern China, arguing that the roof sealing date was incorrect and that the contract price, not the final settlement, should govern payment calculations. Mr. Xing’an countered that the settlement, signed by Mr. Zhongshan’s representative, confirmed the May 15, 2003, date and that Mr. Zhongshan’s payment shortfall was undisputed.

During the appeal, Mr. Zhongshan submitted new evidence, including a planning authority penalty notice and a supervision company report, to argue that the roof was not sealed until later. Mr. Xing’an objected, noting that the settlement had been affirmed in a prior final judgment. The High People’s Court upheld the trial court’s findings, and Mr. Zhongshan applied for retrial to the Supreme People’s Court, which remanded the case to the High People’s Court.

Court Findings and Judgment

The High People’s Court, sitting as the retrial court, confirmed that the settlement signed by Mr. Zhongshan’s representative established the main structure’s roof sealing date as May 15, 2003. The court held that Mr. Zhongshan’s failure to pay 50 percent of the total project cost by that date constituted a prior breach. Under the contract, Mr. Xing’an had the right to stop work or extend the timeline when the employer defaulted on payment. The court also found that the elevation error and balcony changes were additional, independent grounds for an extension.

The court concluded that Mr. Xing’an’s delivery of the project on October 30, 2003, was not a breach of contract. It affirmed the lower court’s dismissal of Mr. Zhongshan’s claim for liquidated damages and ordered Mr. Zhongshan to bear all litigation costs.

Key Legal Principles

The court applied the principle that a party cannot claim damages for delay if its own prior breach contributed to the delay. Under Chinese contract law, when the employer fails to make progress payments as agreed, the contractor is entitled to suspend work or extend the completion date. The court also emphasized that design changes and site errors provided by the employer are valid grounds for a time extension, even if the contractor does not formally apply for one. The court gave decisive weight to a settlement document signed by the employer’s representative, treating it as conclusive evidence of the construction timeline.

Practical Insights

This case underscores the critical importance of strict compliance with payment schedules in construction contracts. Employers who fail to pay progress amounts on time risk losing the right to claim liquidated damages for delay. Contractors should carefully document all employer-caused delays, including design changes and site errors, and ensure that settlement documents clearly reflect the actual completion dates. Signing a settlement without verifying its contents can be fatal to a later claim. Parties should also be aware that Chinese courts will not enforce penalty clauses when the claiming party is itself in breach.

Legal References

This case was decided under general principles of Chinese contract law, including the provisions on payment obligations, time extensions for employer-caused delays, and the prohibition on claiming damages for delay caused by the claimant’s own breach. The court relied on the prior final judgment in the related payment dispute between the same parties, which had established the total project cost and the contractor’s entitlement to payment.

Disclaimer

This article is for informational purposes only and does not constitute legal advice. Consult a qualified attorney for specific legal matters.

This article is rewritten from public court documents for general reading only. It does not constitute legal advice. Consult a qualified attorney for specific legal matters.

All Real CasesLoan & DebtProperty & Real EstateContract & BusinessConsumer & Daily

About UsPrivacy PolicyDisclaimerContactTerms of Service

© 2026 Real Case Legal. All Rights Reserved.