Menu

HomeAll Real CasesLoan & Debt DisputesProperty & Real EstateContract & BusinessConsumer & Daily
HomeAll Real CasesConstruction Dispute Over CNY 4.1 Million Liquidated Damages Dismissed

Construction Dispute Over CNY 4.1 Million Liquidated Damages Dismissed

All Real CasesJune 19, 2026 5 min read

Construction Dispute Over CNY 4.1 Million Liquidated Damages Dismissed

Case Overview

A construction company in Eastern China sought to recover over 4.14 million yuan in liquidated damages from a contractor for alleged project delays. The Supreme People’s Court remanded the case after a prior appeal, but the High Court ultimately found that the developer’s own payment defaults and design changes justified the contractor’s extended timeline. The claim for liquidated damages was denied, reinforcing that a party cannot demand performance penalties when it has materially breached the contract first.

Case Background and Facts

In June 2002, a company referred to as Mr. Zhong’s company (the developer) and a company referred to as Mr. Xing’s company (the contractor) entered into a construction contract for a teacher housing project in Eastern China. The contract set the completion date for October 15, 2003, and stipulated that if the contractor delayed, it would pay liquidated damages of one percent of the total project cost per day. The total project cost was later confirmed at 8,123,157.83 yuan.

The contractor completed the project on October 30, 2003. The developer argued that this was 51 days late, from the contractual date of October 15, 2003, and sought liquidated damages of 4,142,810.49 yuan. The contractor countered that the delay was caused by the developer’s failures, including late payments, incorrect elevation data provided by the developer that required re-excavation of foundation work, and multiple design changes during construction, including modifications to balconies. The contractor also noted that the developer had accepted the project and allowed residents to move in under a supplemental agreement, which it argued constituted an acknowledgment of the completion date.

Court Proceedings and Evidence

The developer initially sued in a local court in Eastern China in January 2007. The contractor responded by pointing to a prior final judgment from the High Court in a related payment dispute, which had already determined that the developer had failed to pay the contractor on time. That prior judgment found that by May 15, 2003, when the main structure was topped out, the developer should have paid 50 percent of the total contract price, or approximately 4,061,578.91 yuan. However, the developer had only paid 1,720,410 yuan by that date.

The developer presented new evidence in the High Court appeal, including a planning authority penalty notice from May 2003 showing that only one floor was completed at that time, and a construction report indicating that work had halted for the winter and resumed in April 2003. The developer argued these documents proved the main structure could not have been topped out by May 15, 2003. The contractor maintained that these were not new evidence and that the prior judgment had already settled the issue.

The High Court reviewed the contractor’s settlement document, which was signed by the developer’s representative and had been admitted as evidence in prior litigation. That document explicitly listed a claim for payment delay losses from May 15, 2003, to November 30, 2003, confirming that the developer acknowledged the main structure was completed on May 15, 2003.

Court Findings and Judgment

The High Court upheld the lower court’s decision and dismissed the developer’s claim. The court found that the developer had materially breached the contract by failing to make timely payments. Under the contract, if the developer failed to pay as agreed, the contractor had the right to stop work or extend the construction period. Since the developer was in default first, the contractor’s delivery on October 30, 2003, was not a breach.

The court also found that the developer’s provision of incorrect elevation data and its instructions for design changes, including balcony modifications, constituted additional work that justified a further extension of the construction period. The developer’s argument that the main structure was not completed until August 2003 was rejected, as the signed settlement document and prior court rulings had already established the May 15, 2003 completion date.

Key Legal Principles

The court applied the principle that a party seeking to enforce a penalty clause must itself have performed its own obligations under the contract. A party that has materially breached the contract cannot demand liquidated damages from the other party for delays caused or contributed to by its own default. The court also recognized that design changes and errors in project specifications provided by the developer are valid grounds for a contractor to claim an extension of time.

Practical Insights

This case illustrates the importance of strict compliance with payment schedules in construction contracts. Developers who fail to pay on time risk losing the right to claim liquidated damages for delays. It also highlights the evidentiary value of signed settlement documents and prior court judgments. Parties should carefully document all design changes and site conditions, as these can serve as a defense against delay claims. Finally, the case shows that courts will look at the entire course of conduct, not just isolated contract clauses, when determining who is responsible for a project delay.

Legal References

Relevant provisions of the Contract Law of the People’s Republic of China concerning breach of contract and liquidated damages, as well as the principle of good faith in contractual performance, were applied. The court also referenced the general rule that a party cannot benefit from its own wrongdoing.

Disclaimer

This article is for informational purposes only and does not constitute legal advice. Consult a qualified attorney for specific legal matters.

This article is rewritten from public court documents for general reading only. It does not constitute legal advice. Consult a qualified attorney for specific legal matters.

All Real CasesLoan & DebtProperty & Real EstateContract & BusinessConsumer & Daily

About UsPrivacy PolicyDisclaimerContactTerms of Service

© 2026 Real Case Legal. All Rights Reserved.