Menu

HomeAll Real CasesLoan & Debt DisputesProperty & Real EstateContract & BusinessConsumer & Daily
HomeAll Real CasesVoyage Charter Dispute: Court Rejects 95.7 Metric Ton Oil Shortage Claim, Upholds Carrier Liability

Voyage Charter Dispute: Court Rejects 95.7 Metric Ton Oil Shortage Claim, Upholds Carrier Liability

All Real CasesJune 14, 2026 5 min read

Voyage Charter Dispute: Court Rejects 95.7 Metric Ton Oil Shortage Claim, Upholds Carrier Liability

Case Overview

In a 2011 voyage charter dispute from Eastern China, the appellate court upheld a lower court ruling dismissing a cargo shortage claim of approximately 95.7 metric tons of crude oil. The charterer alleged that the carrier delivered significantly less net oil than loaded, based on a disputed pre-discharge survey certificate. The court found that the survey certificate was unreliable due to serious procedural defects, including the use of unqualified personnel for sampling. The carrier was held not liable for the alleged shortage.

Case Background and Facts

On September 30, 2009, Mr. Wang’s shipping company (the carrier) and Mr. Wang’s oil products company (the charterer) entered into a voyage charter contract. The carrier agreed to transport 1,000 metric tons of fuel oil (crude oil) from a port in Southern China to a port in Northern China on its vessel. The freight was set at 170 yuan per ton, with a total minimum charge of 170,000 yuan. The contract specified that cargo would be measured at both loading and discharge ports by a surveyor at the ship’s tank hatch. A 3‰ loss allowance was agreed upon, with the carrier responsible for any excess.

The vessel arrived at the loading port on October 2, 2009, and completed loading on October 5. A survey at the loading port measured the cargo volume and found a water content of 4.25%. The vessel arrived at the discharge port on October 21. A pre-discharge survey, conducted by a different survey company, reported a significantly higher water content of 14.05%, resulting in a calculated net oil shortage of 95.7 metric tons. The charterer refused to pay the full freight and later filed a counterclaim for the shortage.

Court Proceedings and Evidence

The carrier initiated a lawsuit to recover the unpaid freight. The charterer filed a counterclaim, seeking compensation for the alleged shortage of 92.974 metric tons (after the 3‰ allowance), totaling 353,766 yuan, plus interest. The carrier later withdrew its claim after the freight was paid, and the case proceeded on the counterclaim only.

A key piece of evidence was the pre-discharge survey certificate. The carrier challenged its validity, presenting a written statement from the survey company and the named inspector. This statement confirmed that the actual sampling and weighing were not performed by the named inspector or any qualified employee of the survey company. Instead, the work was done by an employee of a different company who did not hold the required national qualifications for sampling. The charterer argued this statement was unreliable and that the certificate was valid. The charterer also introduced evidence of the cargo settlement with its buyer to prove its loss.

Court Findings and Judgment

The trial court dismissed the charterer’s counterclaim. The appellate court affirmed this decision. The court held that the dispute centered on whether a cargo shortage existed, which should be determined by comparing the loading and discharge port surveys as per the contract.

The court found the pre-discharge survey certificate to be unreliable and inadmissible. The evidence showed that the named inspector did not conduct the inspection and that the actual sampling was performed by an unqualified individual. This was a serious procedural defect that undermined the certificate’s credibility. Without a valid discharge port certificate, the charterer could not prove that a shortage occurred.

The court also noted that the charterer failed to provide sufficient evidence of actual financial loss, such as a trade contract or invoices, to substantiate its claim for damages. The charterer’s appeal was therefore rejected, and the original judgment was upheld.

Key Legal Principles

This case illustrates the principle that a party claiming a breach of contract, such as a cargo shortage, bears the burden of proof. The evidence must be reliable and obtained in accordance with contractual and regulatory standards. A survey certificate can be deemed invalid if the inspection was not conducted by qualified personnel as required by law. The court will strictly scrutinize evidence that is procedurally defective.

Practical Insights

This case highlights the critical importance of ensuring that all cargo surveys, especially at the discharge port, are conducted by properly qualified and independent inspectors. Charterers and cargo receivers should verify the credentials of the survey personnel and ensure the inspection process is transparent. Carriers should document any irregularities in the survey process to protect themselves from false shortage claims. A party cannot rely on a defective survey to prove a loss, even if the results appear to show a discrepancy.

Legal References

Civil Procedure Law of the People’s Republic of China (2007 Revision), Article 153, Paragraph 1, Item (1). This provision governs the appellate court’s standard of review, allowing it to affirm a lower court judgment that is based on clear facts and correct application of the law.

Disclaimer

This article is for informational purposes only and does not constitute legal advice. Consult a qualified attorney for specific legal matters.

This article is rewritten from public court documents for general reading only. It does not constitute legal advice. Consult a qualified attorney for specific legal matters.

All Real CasesLoan & DebtProperty & Real EstateContract & BusinessConsumer & Daily

About UsPrivacy PolicyDisclaimerContactTerms of Service

© 2026 Real Case Legal. All Rights Reserved.