Menu

HomeAll Real CasesLoan & Debt DisputesProperty & Real EstateContract & BusinessConsumer & Daily
HomeAll Real CasesConstruction Dispute Over Unpaid 279,200 Yuan and Labor Insurance Fund in Eastern China

Construction Dispute Over Unpaid 279,200 Yuan and Labor Insurance Fund in Eastern China

All Real CasesJune 8, 2026 6 min read

Construction Dispute Over Unpaid 279,200 Yuan and Labor Insurance Fund in Eastern China

Case Overview

A Chinese civil court in Eastern China ruled on a dispute between a natural person contractor and a construction company regarding unpaid project funds and improperly deducted labor insurance fees. The court found that the contract between the parties was invalid due to legal restrictions, but because the project had been completed and accepted, the contractor was entitled to payment. The court ordered the construction company to pay outstanding project funds of 279,200 yuan, plus interest, and to return over-deducted labor insurance fees of 180,695.44 yuan.

Case Background and Facts

In 2006, a development company in Eastern China (the owner) entered into a construction contract with a construction company (the first defendant) to build a residential relocation project. Later that year, the construction company subcontracted the work for three specific buildings to an individual contractor (the plaintiff). The plaintiff and the construction company signed a project contracting agreement in October 2006. Under this agreement, the plaintiff was responsible for materials, labor, quality, and safety. The project was completed between May and June 2008, and all three buildings passed final inspection. The total project cost was determined to be 5,905,096 yuan.

The payment terms in the agreement required the plaintiff to finance construction up to the third floor. After that, the construction company would pay 70 percent of the monthly completed work. Upon final acceptance, cumulative payments would reach 70 percent of the single building cost. Within six months after completion, a final audit would be completed, and payment would reach 95 percent of the audited amount. The remaining 5 percent would be paid after the warranty period expired. The agreement also stated that the construction company would deduct 8 percent for various taxes and fees, and that the labor insurance fund would be deducted by the owner.

Court Proceedings and Evidence

The plaintiff filed a lawsuit claiming that the construction company still owed 279,200 yuan in project funds. The plaintiff also alleged that the construction company had improperly deducted 3.4 percent for a labor insurance fund, totaling 200,773.26 yuan, when the contract specified this deduction should come from the owner. Additionally, the plaintiff sought interest for delayed payment of 1.9 million yuan and compensation for work stoppage losses of 420,950.76 yuan.

The construction company admitted owing 279,200 yuan but disputed the other claims. It argued that the 3.4 percent deduction was for a legally mandated labor insurance fund, not a tax or fee, and that the plaintiff had never objected during the project. Regarding the work stoppage, the construction company stated that the plaintiff had already received 408,313 yuan in compensation and that no further amounts were owed. The owner argued that it had no direct relationship with the plaintiff and had already settled all payments with the construction company.

The court reviewed evidence including the contracting agreement, construction contract, inspection reports, payment records, and an arbitration award from a related dispute between the construction company and the owner. The court also examined financial documents showing payment history and deductions.

Court Findings and Judgment

The court held that the project contracting agreement between the plaintiff and the construction company was invalid. The plaintiff, as an individual, could not legally enter into such a contract under Chinese law. However, because the project had been completed and accepted, the plaintiff was entitled to payment based on the contract terms.

The court found that the construction company owed 279,200 yuan in unpaid project funds and ordered payment with interest from July 9, 2010. The court also determined that the construction company had delayed payment of 1,486,873 yuan. The contract required payment of 95 percent of the audited amount by December 12, 2008, but the construction company still owed this amount on June 29, 2009. The court calculated interest on this delayed payment at 122,544 yuan.

Regarding the labor insurance fund, the court found that the contract clearly stated this fund would be deducted by the owner, not the construction company. The construction company had improperly deducted 3.4 percent from the plaintiff’s payments. After accounting for a partial refund of 20,077.52 yuan, the court ordered the return of the remaining 180,695.44 yuan.

The court rejected the plaintiff’s claim for additional work stoppage losses, noting that the plaintiff had already received 408,313 yuan and failed to prove any further entitlement. The court also held that the owner bore no liability because it had paid all amounts owed to the construction company by June 29, 2010.

Key Legal Principles

The court applied the principle that contracts violating mandatory legal provisions are invalid. Under Chinese law, a natural person cannot serve as a contractor for a construction project in the same manner as a licensed construction company. However, the court also applied the rule that if a project is completed and accepted, the contractor may claim payment based on the contract terms, even if the contract itself is invalid. The court further applied the principle that parties must strictly follow contractual terms regarding deductions and that labor insurance funds, when specified to be deducted by a particular party, cannot be unilaterally deducted by another.

Practical Insights

This case illustrates the risks of entering into construction contracts as an individual without proper licensing. While the court allowed payment based on the completed work, the contract was deemed invalid from the start. Parties should ensure they have the proper legal capacity to enter into construction agreements. The case also shows the importance of clearly specifying which party is responsible for specific deductions such as labor insurance funds. When contract terms are clear, courts will enforce them even against the party that actually made the deductions. Finally, the case demonstrates that project owners may avoid liability if they can prove they have paid all amounts due to the main contractor.

Legal References

Contract Law of the Peoples Republic of China, Article 52 (invalidity of contracts violating mandatory provisions)
Supreme Peoples Courts Interpretation on Issues Concerning the Application of Law in Cases of Construction Project Contract Disputes, Articles 2 and 17 (right to payment for completed projects under invalid contracts and calculation of interest)

Disclaimer

This article is for informational purposes only and does not constitute legal advice. Consult a qualified attorney for specific legal matters.

This article is rewritten from public court documents for general reading only. It does not constitute legal advice. Consult a qualified attorney for specific legal matters.

All Real CasesLoan & DebtProperty & Real EstateContract & BusinessConsumer & Daily

About UsPrivacy PolicyDisclaimerContactTerms of Service

© 2026 Real Case Legal. All Rights Reserved.