Menu

HomeAll Real CasesLoan & Debt DisputesProperty & Real EstateContract & BusinessConsumer & Daily
HomeAll Real CasesElevator Company Wins Payment Dispute Over 35,000 RMB in Equipment Contract Case

Elevator Company Wins Payment Dispute Over 35,000 RMB in Equipment Contract Case

All Real CasesMay 30, 2026 4 min read

Elevator Company Wins Payment Dispute Over 35,000 RMB in Equipment Contract Case

Case Overview
A Chinese elevator company sued a construction firm for failing to pay the final installment of 35,000 RMB under an elevator equipment purchase contract. The court ruled in favor of the elevator company, ordering the defendant to pay the outstanding balance plus liquidated damages of 1,260 RMB. The case highlights the enforceability of contract terms and the consequences of non-payment in commercial transactions.

Case Background and Facts
In August 2007, an elevator company based in Eastern China entered into a written contract with a construction company from Central China. The agreement, titled an Elevator and Escalator Equipment Purchase Contract, required the elevator company to supply and deliver three elevators to the construction company. The total contract price was 700,000 RMB. Payment was structured in installments, with the third and final installment of 35,000 RMB due within one week after the expiration of the warranty period.

The elevator company fulfilled all its contractual obligations. The three elevators were installed and passed inspection on August 24, 2009. According to the contract terms, the final payment became due by August 31, 2010. The construction company paid the first two installments but failed to pay the remaining 35,000 RMB. The elevator company initiated legal proceedings to recover the unpaid amount and contractual penalties.

Court Proceedings and Evidence
The case was filed with the court on December 23, 2010. The court applied summary procedures and held a public hearing on January 20, 2011. The elevator company appeared through its authorized representative. The construction company was properly served with legal notice but failed to appear in court without providing any justification. The court proceeded with a default judgment.

The elevator company submitted two key pieces of evidence. The first was the original equipment purchase contract, which established the contractual relationship between the parties. The second was three elevator inspection reports, proving that the elevators had been installed and passed official inspection. Because the defendant did not appear, it was deemed to have waived its right to challenge or cross-examine the evidence. The court found the evidence to be objective, lawful, and valid.

Court Findings and Judgment
The court confirmed that a valid and legally binding sales relationship existed between the parties. The elevator company had performed its duties according to the contract. The construction company, without any legal or contractual justification, failed to pay the remaining balance when it became due. The court held that this constituted a breach of contract, and the defendant was liable for both the outstanding principal and contractual penalties.

The court ordered the construction company to pay the elevator company 35,000 RMB for the equipment and 1,260 RMB in liquidated damages calculated at a daily rate of 0.04 percent from September 1, 2010 to November 30, 2010. Additional damages were to accrue from December 1, 2010 until full payment. The total amount of 36,260 RMB was to be paid within ten days of the judgment taking effect. The court also ordered the defendant to bear the court costs of 353.5 RMB.

Key Legal Principles
The court applied the principle of pacta sunt servanda, meaning agreements must be kept. Under Chinese contract law, a legally formed contract is binding on both parties, and each must perform its obligations. When one party fails to pay a sum certain when due, the other party is entitled to demand payment and seek liquidated damages as agreed in the contract. The court also confirmed that liquidated damages can accrue from the day after the payment deadline.

Practical Insights
This case serves as a reminder that written contracts are enforceable tools for recovering unpaid debts. Businesses should document all agreements in writing and retain evidence of performance, such as inspection reports and delivery receipts. When a buyer fails to pay, the seller can seek both the principal amount and contractual penalties through litigation. Even if the defendant does not appear in court, a default judgment can still be entered based on the plaintiff’s evidence. Including a liquidated damages clause in the contract provides a clear mechanism for calculating compensation for late payment.

Legal References
Contract Law of the Peoples Republic of China, Article 8 (Binding effect of contracts), Article 109 (Payment of monetary obligations), Article 114 (Liquidated damages). Civil Procedure Law of the Peoples Republic of China, Article 130 (Default judgment).

Disclaimer
This article is for informational purposes only and does not constitute legal advice. Consult a qualified attorney for specific legal matters.

This article is rewritten from public court documents for general reading only. It does not constitute legal advice. Consult a qualified attorney for specific legal matters.

All Real CasesLoan & DebtProperty & Real EstateContract & BusinessConsumer & Daily

About UsPrivacy PolicyDisclaimerContactTerms of Service

© 2026 Real Case Legal. All Rights Reserved.